study more about provisional sums from my latest post
Mora QS
Connecting University of Moratuwa Quantity Surveyors across the globe.
Sharing industry insights, project management tips, and collective expertise of Sri Lanka's leading construction professionals.โค๏ธ
Join the UoM legacy in construction excellence.๐ท๐๏ธ
24/03/2026
๐๏ธ Mastering Construction Contracts: What is a Provisional Sum? ๐ ๏ธ
Ever wonder how construction projects handle parts of a building that aren't fully designed yet? Thatโs where Provisional Sums (PS) come in!
What is it? ๐ A Provisional Sum is a specific amount included in a contract for works, materials, plant, or services that cannot be fully measured or described at the time of the agreement
The Two Main Types: โ๏ธ
Defined PS: The work isn't fully designed, but the contract provides the nature of the work, its location, the scope/quantity, and any specific limitations
Undefined PS: This sum is provided when the detailed information required for a "defined" sum simply isn't available yet
How it Works in Practice: โ๏ธ
Fixed Amount: A specific figure (e.g., Rs. 900,000 for landscaping or Rs. 1.5M for security systems) is inserted into the Bill of Quantities (BOQ)
Instruction: During construction, the Engineer identifies and instructs the work to be carried out
Ex*****on: The Contractor or a Nominated Subcontractor executes the task
Payment: Instead of the original estimate, the Contractor is paid the actual cost plus overheads and profit
For Nominated Subcontractors, the payment includes actual amounts plus a fee for attendance (general or special services) provided by the main contractor
Why use them? ๐ค They are essential for anticipated works without firm designs or for work handled by statutory undertakers
This ensures the project keeps moving even when every detail isn't finalized on day one! ๐๏ธ๐
๐ Master Class: Safeguarding the Project: Understanding Performance Security (FIDIC Clause 4.2) ๐
In large-scale construction, trust is essential, but "Performance Security" is the contractual guarantee that ensures the work actually gets done. Under the FIDIC Red Book (1999), this is a critical requirement for every Contractor.
Here is what you need to know about the "rules of engagement" for Performance Security:
1. The 28-Day Countdown โณ
Timing is everything. Once a Contractor receives the Letter of Acceptance, the clock starts ticking. They must deliver the Performance Security to the Employer within 28 days. A copy must also be sent to the Engineer.
Pro Tip: If the security isn't received, the Employer has the right to withhold access to the site!
2. How Long Does It Last? ๐๏ธ
The security isn't just for the construction phase. It must remain valid and enforceable until the Contractor has:
๐Executed and completed the entire Works.
๐Remedied any defects identified during the project. If the security has an expiry date and the work isn't done yet, the Contractor must extend it at least 28 days before it expires.
3. When Can an Employer Make a Claim? ๐ฉ
This is not a "blank check." The Employer can only claim under specific circumstances, such as:
๐Failure to extend validity: If the Contractor doesn't renew a looming expiry.
๐Unpaid debts: If the Contractor fails to pay an agreed or determined amount within 42 days.
๐Failure to remedy: If a default isn't fixed within 42 days of a formal notice.
๐*Termination: If the Employer becomes entitled to terminate the contract.
4. The Final Handover ๐ค
Once the project is truly finished and the Performance Certificate is issued, the Employer must return the Performance Security to the Contractor within 21 days.
Key Takeaway: Performance Security provides the Employer with financial peace of mind while placing a clear responsibility on the Contractor to maintain quality and momentum until the very end.
17/03/2026
๐ Master Class: Safeguarding the Project: Understanding Performance Security (FIDIC Clause 4.2) ๐
In large-scale construction, trust is essential, but "Performance Security" is the contractual guarantee that ensures the work actually gets done. Under the FIDIC Red Book (1999), this is a critical requirement for every Contractor.
Here is what you need to know about the "rules of engagement" for Performance Security:
1. The 28-Day Countdown โณ
Timing is everything. Once a Contractor receives the Letter of Acceptance, the clock starts ticking. They must deliver the Performance Security to the Employer within 28 days. A copy must also be sent to the Engineer.
Pro Tip: If the security isn't received, the Employer has the right to withhold access to the site!
2. How Long Does It Last? ๐๏ธ
The security isn't just for the construction phase. It must remain valid and enforceable until the Contractor has:
๐Executed and completed the entire Works.
๐Remedied any defects identified during the project. If the security has an expiry date and the work isn't done yet, the Contractor must extend it at least 28 days before it expires.
3. When Can an Employer Make a Claim? ๐ฉ
This is not a "blank check." The Employer can only claim under specific circumstances, such as:
๐Failure to extend validity: If the Contractor doesn't renew a looming expiry.
๐Unpaid debts: If the Contractor fails to pay an agreed or determined amount within 42 days.
๐Failure to remedy: If a default isn't fixed within 42 days of a formal notice.
๐*Termination: If the Employer becomes entitled to terminate the contract.
4. The Final Handover ๐ค
Once the project is truly finished and the Performance Certificate is issued, the Employer must return the Performance Security to the Contractor within 21 days.
Key Takeaway: Performance Security provides the Employer with financial peace of mind while placing a clear responsibility on the Contractor to maintain quality and momentum until the very end.
21/02/2026
Ever wondered how a professional private and individual bidding process actually works? ๐๏ธ
Navigating the journey from a project's inception to the final handshake involves a structured, multi-step flow to ensure the best outcome for everyone involved. According to the process outlined, here is a breakdown of the key stages,
๐ Phase 1: Preparation & Approval It all starts with selecting the right consultant and preparing the detailed bid document. If necessary, these plans are submitted for the employer's approval before moving forward.
๐ข Phase 2: The Call for Bids Once the foundation is set, the process moves to the invitation of bids and the formal issuing of the bid documents to interested parties.
๐ Phase 3: Submission & Evaluation This is a critical juncture! Bids are submitted and opened, followed by a thorough evaluation. The consultant then prepares an evaluation report for the employer to review.
๐ค Phase 4: Finalizing the Agreement The final stretch involves direct negotiation to ensure all terms are met before the official Award of the Contract.
Understanding this structured workflow is vital for maintaining transparency and efficiency in private projects. Which part of the bidding cycle do you find the most complex? Letโs discuss in the comments! ๐
21/02/2026
๐ฆ๐๐ค๐ฆ-๐จ๐๐: ๐๐๐ก๐๐ฅ๐๐ ๐๐ฃ๐ ๐ญ ๐ฎ๐ฌ๐ฎ๐ฒ/๐ฎ๐ฌ๐ฎ๐ณ (๐๐ฟ๐ฒ๐ฒ ๐ผ๐ณ ๐๐ต๐ฎ๐ฟ๐ด๐ฒ โ ๐๐ถ๐บ๐ถ๐๐ฒ๐ฑ ๐ฆ๐ฒ๐ฎ๐๐ ๐ข๐ป๐น๐)
๐ง๐ผ๐ฝ๐ถ๐ฐ:
๐ฅ๐๐๐ฆ ๐๐ฃ๐ ๐ฆ๐๐ฝ๐ฝ๐ผ๐ฟ๐ & ๐๐ถ๐ป๐ฎ๐น ๐๐๐๐ฒ๐๐๐บ๐ฒ๐ป๐ ๐ฃ๐ฟ๐ฒ๐ฝ๐ฎ๐ฟ๐ฎ๐๐ถ๐ผ๐ป
As part of SLQS-UAEโs commitment to professional excellence and โDelivering Diligenceโ, we are pleased to conduct General CPD 1 for the 2026/2027 cycle in collaboration with the Royal Institution of Chartered Surveyors (RICS).
This session provides a valuable opportunity to gain authoritative guidance directly from RICS, offering clear insight into assessment expectations, common referral pitfalls, documentation standards, and structured preparation strategies to confidently approach the APC Final Assessment.
๐๐๐ฒ๐๐ ๐ฆ๐ฝ๐ฒ๐ฎ๐ธ๐ฒ๐ฟ
๐ ๐. Archana Dutt
Senior Manager โ Early Years & Candidate Engagement
APAC, MEA & South Asia
Royal Institution of Chartered Surveyors
๐๐ฎ๐๐ฒ: Wednesday, 25 February 2026
๐ง๐ถ๐บ๐ฒ: 7:30 pm โ 9:30 pm (UAE time)
๐ฉ๐ฒ๐ป๐๐ฒ:
Badiyah Hall at Mercure Dubai Hotel
Barsha Heights, Dubai
๐ฅ๐ฒ๐ด๐ถ๐๐๐ฟ๐ฎ๐๐ถ๐ผ๐ป ๐๐ถ๐ป๐ธ:
https://lnkd.in/dgcS8vju
Registration will be on a first-come, first-served basis.
For more information, please refer to the attached flyer.
Warm regards,
SLQS-UAE
Copyright goes original owner.